单选题:The following figure shows the AOE network of a project with 8 a

Luz5年前 (2021-05-10)题库772
The following figure shows the AOE network of a project with 8 activities. The earliest and the latest completion times of the activity `d` are __, respectively. @[C](2)

![GRE19-5.jpg](~/28de33de-076f-4f94-b856-445865994fb0.jpg)

A. 3 and 7
B. 12 and 12
C. 12 and 14
D. 15 and 15




A.3 and 7
B.12 and 12
C.12 and 14
D.15 and 15


答案:C