单选题:The software equation can be used to show that by extending the

Luz5年前 (2021-05-10)题库718
The software equation can be used to show that by extending the project deadline slightly __. @[A](1)

A. fewer people are required
B. you are guaranteed to meet the deadline
C. more lines of code can be produced
D. fewer bugs can be produced




A.fewer people are required
B.you are guaranteed to meet the deadline
C.more lines of code can be produced
D.fewer bugs can be produced


答案:A