单选题:Given the AOE network of a project with 8 activities shown below

Luz5年前 (2021-05-10)题库1240
Given the AOE network of a project with 8 activities shown below, the earliest/latest completion time for node `4` is __. @[C](2)


![Untitled.png](~/7d0cbf20-30bc-4946-b8ce-3a4697c01712.png)



A. 8 and 8
B. 10 and 16
C. 10 and 10
D. 8 and 14




A.8 and 8
B.10 and 16
C.10 and 10
D.8 and 14


答案:C