单选题:Given the AOE network of a project with 8 activities shown below

Luz5年前 (2021-05-10)题库1403
Given the AOE network of a project with 8 activities shown below, the earliest/latest completion time for node `2` is __. @[C](2)


![Untitled.png](~/7d0cbf20-30bc-4946-b8ce-3a4697c01712.png)



A. 3 and 8
B. 3 and 3
C. 3 and 5
D. 5 and 8




A.3 and 8
B.3 and 3
C.3 and 5
D.5 and 8


答案:C