单选题:Given an AOE network of 10 activities as shown below. The activ

Luz3年前 (2022-02-27)题库423
Given an AOE network of 10 activities as shown below. The activity with the longest slack time is:

![AOE网.png](~/fdf0f61d-b9a1-4822-bec3-ebfc04198915.png)




A.c
B.g
C.h
D.j


答案:B