The following figure shows the AOE network of a project with 8 activities. The earliest and the latest completion times of the vertex `4` are __, respectively.


![AOE.jpg](~/3c300bf3-1c56-455c-bf88-51ae8b52e106.jpg)

@[C](2)

A. 12 and 12
B. 12 and 14
C. 19 and 19
D. 19 and 23



A.12 and 12
B.12 and 14
C.19 and 19
D.19 and 23


答案:C